Install your Tower Base

Step 1 - Dig foundation hole per dimension specifications.   Step 2 - Level hole bottom & dig in the perimeter toe, install 4” solid blocks.   Step 3 - Tie the two levels of rebar to the direct embedment section (DES) per drawing.
   
Step 4 - Lift lower the DES with tied rebar into the excavation.   Step 5 - Straighten level the DES using 3 cable comalongs, then form & level the top hole perimeter.   Step 6 - Pour, vibrate concrete with a crown in center, trowel finish & cover with plastic tarp for 24 hours minimum.
   

 